12
PM Interval: 3 Months Date: / /
Equipment: W/O # Location:
Mechanic: Serial # Model #
Check Appropriate Box. “”
MAXON 1
st
, 2
nd
and 3
rd
Quarter Liftgate PM Procedures
Satisfactory Repair Required Corrected
1
Verify if the Quarterly or Annual PM is due by checking the PM sticker on
the roadside Liftgate column
Satisfactory Repair Required Corrected
2
Check for oil leaks at: cylinders, ttings, hoses, valves, oil lter and
ttings inside of pump box
Satisfactory Repair Required Corrected
3
Check for damage: bent ramps, platform, column, runners and hydraulic
tubes
Satisfactory Repair Required Corrected
4 Check for loose or missing nuts, bolts, covers, roll pins, screws and pins
Satisfactory Repair Required Corrected
5
Check for cracked welds at: columns, runners, platform, chain arms,
pump box and door frame
Satisfactory Repair Required Corrected
6
Check platform lowering speed: Range is 15-25 seconds. Check “D”
valves for proper operation
Satisfactory Repair Required Corrected
7 Check platform pins and couplers. Check roller assemblies
Satisfactory Repair Required Corrected
8 Check platform raising speed: Range is 20-40 seconds
Satisfactory Repair Required Corrected
9
Check open and close speed: Range is 4-7 seconds in either direction.
Adjust if necessary
Satisfactory Repair Required Corrected
10
Check switches, circuit breaker and wiring connections at the gate as
well as inside pump box. Also check ground straps
Satisfactory Repair Required Corrected
11
Check the gear pump for unusual noise. i.e. squealing or extreme RPM
output
Satisfactory Repair Required Corrected
12
Checking Oil Level: gravity down with the Liftgate open and on the
ground the sight glass should be at half level. Power down open Liftgate
and raise to bed height the sight glass should be at half level. Check for
contamination, change if needed
Satisfactory Repair Required Corrected
13 Check batteries: load test, corrosion, cables, hold downs and water level
Satisfactory Repair Required Corrected
14
Dual pump units: Please switch the selector switch to opposite assembly
at each PM
Satisfactory Repair Required Corrected
15 Check chains for twisting
Satisfactory Repair Required Corrected
16 Check operation of cart stop ramps
Satisfactory Repair Required Corrected
17 Check all charging and ground cable connections
Satisfactory Repair Required Corrected
18
Complete a new PM sticker and install it on the roadside column of the
Liftgate. The next PM date is 3 months from the completed PM date.
Indicate on the PM sticker if 1
st
, 2
nd
, 3
rd
or 4
th
PM
MAXON 4
th
Liftgate PM. Note: Includes steps 1-18
Satisfactory Repair Required Corrected
19 Replace spin on lter in pump box. Change hydraulic uid
Satisfactory Repair Required Corrected
20 Inspect wear on slide pads. See if shimming is required
For more detailed information, please refer to the product maintenance manuals. Use only genuine Maxon replacement
parts for all repairs.
MAXON BMR-A LIFTGATE
PREVENTATIVE MAINTENANCE CHECKLIST
TABLE 12-1
PERIODIC MAINTENANCE
Seitenansicht 11
1 2 ... 7 8 9 10 11 12 13 14 15 16 17 ... 85 86

Kommentare zu diesen Handbüchern

Keine Kommentare